Program Discipline: Civil, Structure, Mechanical, Electrical, Instrumentation, and Process

Contract: AS 4300

Anticipated population growth within the current and future catchment areas of the Aldinga Wastewater Treatment Plant suggest that existing infrastructure at the Aldinga Wastewater treatment plant will not be able to manage forecast inflows.

The key objective of this project is to ensure the capacity and performance of the Aldinga Wastewater Treatment Plant asset is adequate to accommodate the immediate and long term treatment requirements to treat the wastewater generated by the population served by the connected wastewater network.
This project requires thorough stakeholder management with internal and external stakeholders. In general below works will be delivered under Aldinga Waste Water Treatment Program:

• Construct new inlet works (124L/s)
• Construct a Primary Sedimentation Tank
• Infrastructure to allow tankering of the primary sludge to Christies Beach for digestion
• Construct new pump station (and hydraulic modifications) to Christies Beach WWTP outfall
• Rehabilitation of Storage area