As part of SA Water RBP20 (and beyond) work, I led the engineering and long term asset planning works for the Glenelg, Aldinga, and Christies Beach Wastewater Treatment Plant (WWTP). The objective of these projects was to determine how to manage each asset at its... by admin | Nov 1, 2016 | Programs & Projects
Program Discipline: Civil & Structure Contract: AS 4300 by admin | Oct 1, 2016 | Programs & Projects
Program Discipline: Mechanical, Civil Contract: AS 2124 Water Main Relay Program (WMR) has been proposed by SA Water Asset Management in accordance with the annual process of selecting priority mains for relay. The number of customers affected due to pipe bursting and... by admin | Sep 1, 2016 | Programs & Projects
Program Discipline: Civil, Structure, Mechanical, Electrical, Instrumentation, and Process Contract: AS 4300 Anticipated population growth within the current and future catchment areas of the Aldinga Wastewater Treatment Plant suggest that existing infrastructure at... by admin | Aug 1, 2016 | Programs & Projects
Program Discipline: Mechanical 2012/13 WMR Program consisted of 34 projects which resulted in 14.3km water mains’ renewal.